| Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Status | ||
|---|---|---|---|---|---|---|---|
| Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
| Project Milestone-I | 160 | 20 | 20.08.2023 | 15.05% | |||
| Project Milestone-II | 360 | 35 | 08.12.2023 | ||||
| Project Milestone-III | 485 | 75 | 12.06.2024 | ||||
| Schedule Completion | 730 | 100 | 10.12.2024 | ||||